Construction work on the Remetinec roundabout is entering its final phase. Construction work on the underpass construction, the construction of the new traffic roundabout ring, and access ramps are being completed.
At this point, it is necessary to connect the Adriatic Bridge to the traffic surfaces of the new Remetinec roundabout. Therefore, changes to the temporary traffic regulation will be made during October and November, and parts of the new roundabout will be used for faster and safer traffic. The works will be carried out in two phases.
Phase 1
In the first phase, which will last from 20 October 2019. from 5 a.m., the western pavement of the Adriatic Bridge will be started.
The redistribution of the bands is as follows:
Phase 2
In Phase 2 which will run from 17 November 2019 from 5 a.m., the east pavement and part of the bridge are regulated and the traffic regulation is as follows: